Below are samples of the projects carried out by both our affiliates, Scope Trading and WTR Contracting for the
last two years. |
|
Red Crescent Baghdad Branch
Design and Construct office for RC Baghdad branch.
Total area is 650 sq. meters.
Construction period: 24 weeks.
Status: completed.
Total cost: $ 105,000.00
|
 |
UNDESA HQ in Baghdad
Total rehabilitation of old office building in center of Baghdad.
Total area 1,246 sq. meters.
Rehabilitation period: 36 weeks.
Status: completed.
Total cost: $ 180,000.00
Work included car park, HVAC equipment and LAN wiring. |
 |
LRC Building—UNDP, Baghdad
Total rehabilitation of old office building adjacent to the UNDP offices in Abu Nawas St.
Rehabilitation period: 32 weeks.
Status: completed.
Total cost: $ 94,500.00
Work included car park, HVAC equipment and LAN wiring. |
 |
Ataeej Water Treatment Plant
Installation of electromechanical WTP and all required civil works in Hilla.
Work period: 12 weeks.
Status : completed.
Total cost: $ 145,000.00 |
 |
Babel Cinema
Partial rehabilitation of Babel cinema in Baghdad. Including repair of damages resulting from air bombing.
Work period: 10 weeks.
Status: completed.
Total cost: $ 45,000.00 |
 |
Supply of A/C Parts
Supply the General Electrical Industries Co. ( the largest manufacturer an Iraq) of air conditioning parts.
Total amount of contract: $ 80,000.00 |
 |
Supply of CKD Equipment
Supply the General Electrical Industries Co. ( the largest manufacturer an Iraq). CKD air conditioning equipment, both window type and split units.
Total Amount of contract: $ 250,000.00 |
 |
Admin Building of ICRC
Design and construct office for ICRC.
Total area is 1050 sq. meters.
Construction period: 52 weeks.
Status: completed.
Total cost: $ 200,000.00 |
 |
Expansion of Islah Water Treatment Plant
Expansion of plant in Nassiriya, including design and construction of steel pressure tank and booster station.
Work period: 12 weeks.
Status: completed.
Total Cost: $ 140,000.00 |
 |
Supply of A/C Parts
Supply the General Electrical Industries Co. ( the largest manufacturer in Iraq) of air conditioning parts.
Total amount of contract: $ 107,000.00 |
 |
Expansion of Shatra Water Treatment Plant
Design and construct low lift pump station, as under water concrete structure including supplying submersible pumps, control boards and all piping necessary.
Work period: 52 weeks,
Status: completed.
Total cost: $ 650,000.00 |
 |
Supply of A/C Parts
Supply the General Electrical Industries Co. ( the largest manufacturer an Iraq) of air conditioning parts.
Total amount of contract: $ 92,000.00 |
|
Supply of A/C equipment to Telecom. Co.
Supply and install a/c equipment to the Telecom. co. HQ in Baghdad. Including all necessary cabling and electrical connection. Total amount of contract:
$ 64,000.00 |
|